Task_NameDurationStartFinishCost5/35/105/175/245/316/76/146/216/287/57/12
Gas BOILER #3175/15/156/1/15$2,200
Drain the water from the boiler45/15/155/19/15$0
Open the water and mud drums and hand holds25/20/155/22/15$2,000
Rinse out the drums25/25/155/27/15$0
Open and inspect the water columns and lines45/15/155/19/15$0
Inspect the site glass45/15/155/19/15$0
Remove the baffles from the water drum25/25/155/27/15$0
Turbine tubes if needed45/28/156/1/15$200
Inspect the chemical lines45/15/155/19/15$0
Open up the fire box and inspect the burner45/15/155/19/15$0
Deaerator TANK16/8/156/9/15$300
Drain the water and open the top and bottom doors16/8/156/9/15$300
Remove the grates (trays)16/8/156/9/15$0
Rinse the Deaerator tank out16/8/156/9/15$0
Inspect the shower head16/8/156/9/15$0
Scrape the inside of the tank and look for damage16/9/156/10/15$0
Inspect the injection quill16/9/156/10/15$0
BOILER ROOM16/15/156/16/15$4,600
Repack and rebuild all the steam valves16/15/156/16/15$200
Repack and rebuild all the water valves16/16/156/17/15$200
Open, clean out and inspect the cones in all 3 dust collectors/Replace chain guards16/15/156/16/15$300
Inspect the condensate tank and pumps16/15/156/16/15$0
Have the safety valve on #2 Boiler tested16/15/156/16/15$3,000
Inspect the piping of the feed water line coming out of the bottom of the Deaerator tank16/15/156/16/15$0
Inspect the expansion joints at the feed water pumps16/15/156/16/15$0
Clean the steam header pipes and tops of all three boilers & Deaerator tank16/15/156/16/15$300