State Account Number C8XM
Scope of Work – Total renovation of building’s basement and first floors to create modern spaces for research, teaching and extension for land grant program. The second and third floors will be renovated at a later date when additional funding is available.
Federally approved project cost - $2,296,476. (Approved by Board 9/6/18) Design Phase B documents are complete with an estimated cost of $1,605,688. Anticipated completion date – August 2020.
State Account Number C98B
Scope of work – install power to aeration equipment at raceways used to cultivate fish growth and related research activities.
Estimated cost - $45,000.
Anticipate completion date of September 2019.
State Account Number C96R
Scope of Work – Wiring, piping and foundation work to install fountain in front of Student Center. Construction budget of $60,000. Executing construction contract within the next two weeks. Anticipated completion date of late September 2019.
State Account Number C96S
Scope of Work – Install pedestal and associated landscape features for statuary at west end of ASB parking lot. Phase C Design Documents are complete with an estimated construction cost of $174,000 (not including statuary). Project will be advertised for bidding –Anticipated completion date of late December 2019.