KENTUCKY STATE UNIVERSITY
Board of Regents
State Account Number C756
Scope of Work – Replace coal fired boilers with natural gas boilers and replace distribution lines.
Phase II of replacing aging distribution lines contract of $580,598.11 is awarded to Alpha Mechanical – work to begin October 2019 and completed June 2019.
Smokestack Demolition was bid May 14 – Contract for $44,000 to be awarded to Complete Demolition Services. Work to begin September 2019 and be completed October 2019.
Appropriation - $10,400,000.
State Project # FDo4 SPP 037 0060 009-011
Signal pole relocation – KYTC is negotiating change order with contractor and is to advise KSU of work to begin & completed.
KYTC Funded at $1,820,000.
State Account Number C751
Scope of Work – Total renovation of building to create modern spaces for research, teaching and extension for land grant program.
Construction contract awarded to Redlee Construction – actual work began in June 2019 – completion date is June 2020.
Federally approved cost - $7,428,393.
State Account Number C96U
Scope of Work – Site work, foundations and power supply wiring needed to erect the bell tower.
Current budget estimates are below approved budget amount of $500,000.
Design Phase C work is complete – estimated construction cost is $58,000 (not including tower purchase)
Project will be advertised for bidding –Anticipated completion date of late November 2019.