o Cash Balance: TBD
o Architectural Firm: Omni Architects
o Design Fees Allotment: TBD
Status: This project is currently going through a feasibility study to determine future interior and exterior renovation. Project manager, Carl
Kratzer, with the Division of Engineering and Contract Administration (DECA) has been assigned to this project.
• Jordan Building and Warehouse Roof Replacement 2012
• Renovation - Halls
o State Account No.: C66S
o Fund Source: KSU
o Appropriation: TBD
o Cash Balance: TBD
o Architectural Firm: TBD
o Design Fees Allotment: TBD
o Status: This project has an estimated cost of $41,190.00 to replace the damaged section of the Jordan Building and the Warehouse. Project Manager, Carl Kratzer, with the Division of Engineering and Contract Administration (DECA) has been assigned to this project.
o State Account No.: C8XN
o Fund Source: Institutional
o Budget: Estimated $900,000
o Mold Remediation Firm: Chase Environmental Group, Inc.
o Mechanical Engineering Firm: CMTA Engineers with Hussung Mechanical as subcontractor
o Start: 04/30/2018 – Begin Phase 1 Mold Remediation and Mattress Removal, and complete on 05/05/2018. 05/07/2018 – 05/11/2018: On-site mechanical systems evaluations. Draft report received 05/15/2018.
o Status: Soffits removed. Mechanical evaluation complete. Awaiting scope of work and engineering cost estimate from Division of Engineering and Contract Administration (DECA). ETA unknown.