Review of Campus Facilities and Priorities June 7, 2018

Current Construction

• Repair Boilers and Aging Distribution Lines

  • State Account No.: C756
  • Fund Source: State Bond Authorized in Fiscal Year 2014-2015
  • Appropriation: $10,400,000.00
  • Cash Balance: $-327,586.34
  • Mechanical Engineer Prime Firm: CMTA Consulting Engineers, Prospect, Kentucky
  • Actual Construction cost total with changes: $6,600,107.00
  • Start: 6/13/2016. Substantial: 8/01/2017. Final Completion: 9/01/2017
  • Construction Prime Contractor: Hussung Mechanical Contractors, Louisville, Kentucky
  • Phase I: Status: This project is completed and under a one (1) year warranty.
  • Phase II: Status: This project is completed and under a one (1) year warranty.
  • Phase III: Status: This project is completed and under a one (1) year warranty.

• Pedestrian Bridge across US60

  • State Account No.: 151064
  • Fund Source: KY Transportation Cabinet, Road Funds FY2013
  • Appropriation: $8,200,000.00
  • Civil Engineer Prime Firm: Palmer Engineering, Winchester, Kentucky
  • Actual Construction Cost total with changes: $5,100,000.00
  • Start: 10/27/2015. Final Completion: 6/18/2018. Additional work crews were established to meet the new scheduled completion date.
  • Construction Prime Contractor: Hall Contracting of Kentucky Inc., Louisville, Kentucky
  • Utility Relocation by FPB
  • Construction Cost: $691,342.93