Review of Campus Facilities and Priorities
June 7, 2018
Current Construction
• Repair Boilers and Aging Distribution Lines
- oState Account No.: C756
- oFund Source: State Bond Authorized in Fiscal Year 2014-2015
- oAppropriation: $10,400,000.00
- oCash Balance: $-327,586.34
- oMechanical Engineer Prime Firm: CMTA Consulting Engineers, Prospect, Kentucky
- oActual Construction cost total with changes: $6,600,107.00
- oStart: 6/13/2016. Substantial: 8/01/2017. Final Completion: 9/01/2017
- oConstruction Prime Contractor: Hussung Mechanical Contractors, Louisville, Kentucky
- oPhase I: Status: This project is completed and under a one (1) year warranty.
- oPhase II: Status: This project is completed and under a one (1) year warranty.
- oPhase III: Status: This project is completed and under a one (1) year warranty.
• Pedestrian Bridge across US60
- oState Account No.: 151064
- oFund Source: KY Transportation Cabinet, Road Funds FY2013
- oAppropriation: $8,200,000.00
- oCivil Engineer Prime Firm: Palmer Engineering, Winchester, Kentucky
- oActual Construction Cost total with changes: $5,100,000.00
- oStart: 10/27/2015. Final Completion: 6/18/2018. Additional work crews were established to meet the new scheduled completion date.
- oConstruction Prime Contractor: Hall Contracting of Kentucky Inc., Louisville, Kentucky
- oUtility Relocation by FPB
- oConstruction Cost: $691,342.93