Review of Campus Facilities and Priorities
June 7, 2018
State Account No.: C756
Fund Source: State Bond Authorized in Fiscal Year 2014-2015
Appropriation: $10,400,000.00
Cash Balance: $-327,586.34
Mechanical Engineer Prime Firm: CMTA Consulting Engineers, Prospect, Kentucky
Actual Construction cost total with changes: $6,600,107.00
Start: 6/13/2016. Substantial: 8/01/2017. Final Completion: 9/01/2017
Construction Prime Contractor: Hussung Mechanical Contractors, Louisville, Kentucky
Phase I: Status: This project is completed and under a one (1) year warranty.
Phase II: Status: This project is completed and under a one (1) year warranty.
Phase III: Status: This project is completed and under a one (1) year warranty.
State Account No.: 151064
Fund Source: KY Transportation Cabinet, Road Funds FY2013
Appropriation: $8,200,000.00
Civil Engineer Prime Firm: Palmer Engineering, Winchester, Kentucky
Actual Construction Cost total with changes: $5,100,000.00
Start: 10/27/2015. Final Completion: 6/18/2018. Additional work crews were established to meet the new scheduled completion date.
Construction Prime Contractor: Hall Contracting of Kentucky Inc., Louisville, Kentucky
Utility Relocation by FPB
Construction Cost: $691,342.93