IV. SUMMARY OF COSTS

1.0 All General Construction (including general sitework) $ 3,900

2.0 All Mechanical (exterior & building) $ 395,967

3.0 All Electrical (exterior & building) $ 39,804

4.0 Off-site Utilities (When Applicable) $ -

TOTAL CONSTRUCTION COST ESTIMATE (Base Bid): $ 439,671

V. ADDITIVE ALTERNATES (When Applicable - Requires Project Manager Approval)

1.0 Dayroom Trailer HVAC Upgrade $

TOTAL COMBINED COST: $ 439,671

  • Total Gross Area: - gsf
  • Gross Area (AIA Architectural Area): - gsf
  • Net Assignable Area (Productive Space): - naa % efficient
  • SPACE STUDY STATEMENT
  • Square Foot Costs (Excluding Sitemap) $- /sq ft
  • Square Foot Costs per Net Assignable Area $- /sq ft of naa

Note: All measurements per AIA Method Document D101 (June, 1974). Additional special information relating to this estimate to be attached on seperate sheets.

Design Development:

Time, in calendar days, after receipt of written authorization to complete Phase "B" Plans: 0 Days

Construction Documents:

Time, in calendar days, after approval of Phase "B" to complete Phase "C" Construction Documents, including time necessary to secure all Agency approvals: 45 Days

Bidding, Plan Review & Permitting Time:

Time, in calendar days, to obtain bids, plan review approvals and permits: 60 Days

Construction Time:

Time, in calendar days, after work order is issued to Substantial Completion: 120 Days

Estimate Prepared by: Tom Connolly, PE 7/7/2023

Date:

Estimate Certified by: Tom Connolly, PE 7/7/2023

(Principal of firm) Date:

Estimate Approved by:

Using Agency Representative Date:

Using Agency Representative

Date: