IV. SUMMARY OF COSTS
1.0 All General Construction (including general sitework) $ 3,900
2.0 All Mechanical (exterior & building) $ 395,967
3.0 All Electrical (exterior & building) $ 39,804
4.0 Off-site Utilities (When Applicable) $ -
TOTAL CONSTRUCTION COST ESTIMATE (Base Bid): $ 439,671
1.0 Dayroom Trailer HVAC Upgrade $
TOTAL COMBINED COST: $ 439,671
Total Gross Area: - gsf
Gross Area (AIA Architectural Area): - gsf
Net Assignable Area (Productive Space): - naa % efficient
SPACE STUDY STATEMENT
Square Foot Costs (Excluding Sitemap) $- /sq ft
Square Foot Costs per Net Assignable Area $- /sq ft of naa
Note: All measurements per AIA Method Document D101 (June, 1974). Additional special information relating to this estimate to be attached on seperate sheets.
Design Development:
Time, in calendar days, after receipt of written authorization to complete Phase "B" Plans: 0 Days
Construction Documents:
Time, in calendar days, after approval of Phase "B" to complete Phase "C" Construction Documents, including time necessary to secure all Agency approvals: 45 Days
Bidding, Plan Review & Permitting Time:
Time, in calendar days, to obtain bids, plan review approvals and permits: 60 Days
Construction Time:
Time, in calendar days, after work order is issued to Substantial Completion: 120 Days
Estimate Prepared by: Tom Connolly, PE 7/7/2023
Date:
Estimate Certified by: Tom Connolly, PE 7/7/2023
(Principal of firm) Date:
Estimate Approved by:
Using Agency Representative Date:
Using Agency Representative
Date: