309 - ARCHITECT-ENGINEERS ESTIMATE OF CONSTRUCTION COST
PHASE "A" - SCHEMATIC DESIGN
Project Name: KSU Nutrition Building HVAC
Location: Frankfort, Kentucky
ville No.: 435-CB1E-KS43-00
- I.a. SITE WORK
- 1.0 Demolition $ -
- 2.0 Clearing $ -
- 3.0 Grading $ -
- 4.0 Paving $ -
- 5.0 Concrete $ 3,900
- 6.0 Planting $ -
- 7.0 Miscellaneous Items (Identify) $ -
- c.EXTERIOR ELECTRICAL $ -
- d.UTILITY RELOCATION $ -
- b.EXTERIOR MECHANICAL $ -
- TOTAL SITE WORK: $ 3,900
- II.a. OFF-SITE UTILITIES
- III.a. BUILDING CONSTRUCTION
- General Construction Total: $ -
- 4.0 Control Systems $ -
- Mechanical Subtotal: $ 395,967
- Electric Safety & Security $ -
- Electrical Subtotal: $ 39,804
- TOTAL BUILDING CONSTRUCTION: $ 435,771
- TOTAL SITE WORK, SITE UTILITIES, & BUILDING CONSTRUCTION: $ 439,671
- 1.0 (Identify Utilities) $ -
- TOTAL SITE UTILITIES: $ -
- 1.0 Structural $ -
- 2.0 Architectural $ -
- 3.0 Elevator $ -
- 4.0 Built-in Equipment $ -
- 5.0 Special Items (Identify) $ -
- b.BUILDING MECHANICAL
1.0 Fire Suppression $ -
2.0 Plumbing $ -
3.0 Heating, Ventilation & Air Conditioning $ 395,967
1 Electric Power & Lighting $ 39,804
Communication $ -
c. BUILDING ELECTRICAL
General Site Work Subtotal: $ 3,900