Total Budget$0.00$8,498,878.00
Total Obligated$0.00$6,755,313.93
Total Funds Drawdown$180,852.24$6,261,351.41
Program Funds Drawdown$0.00$5,091,519.72
Program Income Drawdown$180,852.24$1,169,831.69
Program Income Received$32,649.32$2,583,546.27
Total Funds Expended$0.00$8,070,580.49
HUD Identified Most Impacted and Distressed$0.00$0.00
Other Funds$0.00$0.00
Match Funds$0.00$0.00
Non-Match Funds$0.00$0.00
Funds Expended
OverallThis PeriodTo Date
Inland Fair Housing and Mediation Board (IFHMB)$0.00$4,320.00
Victorville Redevelopment Agency1$0.00$8,066,260.49
Progress Toward Required Numeric Targets
RequirementTargetProjectedActual
Overall Benefit Percentage99.99%.00%.00%
Minimum Non Federal Match$.00$.00$.00
Overall Benefit Amount$7,729,453.98$.00$.00
Limit on Public Services$796,704.45$.00$.00
Limit on Admin/Planning$531,136.30$781,136.00$616,285.24
Limit on Admin$.00$781,136.00$616,285.24
Most Impacted and Distressed$.00$.00$.00
Progress towards LH25 Requirement$2,127,840.75$2,930,165.43
Overall Progress Narrative:
No new activities or expenditures to report during 2nd Qtr 2021.
Project Summary
This ReportTo Date
Project #, Project TitleProgram Funds DrawdownProject Funds BudgetedProgram Funds Drawdown
NSP 2008 09-100-10, Acquisition Rehab Rental$0.00$467,672.00$0.00
NSP 2008 09-100-11, Redevelopment$0.00$219,843.00$0.00
NSP 2008-09-100-01, Acquisition, Rehab, Resale$0.00$6,514,625.18$4,237,055.24
NSP 2008-09-100-03, Financial Mechanisms$0.00$269,921.82$250,000.00
NSP 2008-09-100-04, Demolition and Land Banking$0.00$245,680.00$169,031.48
NSP 2008-09-100-09 A, Administration$0.00$781,136.00$435,433.00
Activities
Project # / NSP 2008-09-100-03 / Financial Mechanisms