Capital Budget Record CBR-02
Branch: Executive Branch
Cabinet: Postsecondary Education
Agency: Postsecondary Education Institutions
Appropriation: Kentucky State University
Project Title: E1 Capital Renewal & Maintenance Projects Pool 2014
KBUD Project Number: 435U14C241
PriorityCapital Budget RequestSix-Year Capital Plan 2014-16
Cabinet:
Agency:1414
PROJECT DOCUMENTATION
Location (County): Franklin
Location (ADD): Bluegrass
Reauthorization - Regular Capital Project: Is this a currently authorized project which is being requested for reauthorization and/or additional funding? NO
If (Yes, Additional Funding), provide the following information: eMars Project Number (Agency, Fund): New Total Project Cost: $
Related to Previously Authorized Project: If the project is related to or a new phase of a project which was previously authorized please identify the project and action under which it was authorized.
Capital Project Type: Multiple Project Pool
Project Description
Additional/Description Justification
-Citation, Order, Agreement with State or Federal Courts or a Regulatory Agency - N/A
-Project Measurements - Small projects CR&R pool. Paint interior of 20% of campus buildings - $300,000 Campus wide sprinkler system improvements - $500,000 C
Project Budget
Project budget was based on current estimating practices for similar project types utilizing square foot costs and maintenance cost standards.
Existing Facility
This project is a pool covering various buildings and systems on KSU campus.
Program Relocation
Phased Project
Universities Only: Type of SpaceEducational and General
Proposed Heat/Air conditioning Fuel TypeCoal
Previous Request(s): Has this item been requested in a prior biennial budget request? No
If yes, identify the biennium/biennia; the project names(s); and the Cabinet/Agency.
PROJECT BUDGET
Has this project been reviewed by the Department for Facilities and Support Services? No
Fund SourceRequested FY 2013-14Requested FY 2014-15Requested FY 2015-16Requested Total
Restricted Funds01,460,00001,460,000
Total Funds01,460,00001,460,000
Cost Elements
Construction Costs01,460,00001,460,000
Total Costs01,460,00001,460,000
Completion Date: 05 / 2016
Method of Procurement (Acquisitions Only): Purchase
IMPACT ON OPERATING BUDGETFY1 AmountFY2 AmountFY3 AmountFY4 AmountFY5 Amount
Fund Source

64