2014-2016 Kentucky Branch Budget Capital Budget Request: Capital Project Record All dollar amounts rounded to next $1000

Capital Budget Record CBR-02
Branch:Executive Branch
Cabinet:Postsecondary Education
Agency:Postsecondary Education Institutions
Appropriation:Kentucky State University
Project Title:E2 Develop Bicycle/Pedestrian Trail
KBUD Project Number:435U14C245
PriorityCapital Budget RequestSix-Year Capital Plan 2014-16
Cabinet:
Agency:1313
PROJECT DOCUMENTATION
Location (County): Franklin
Location (ADD): Bluegrass
Reauthorization - Regular Capital Project: Is this a currently authorized project which is being requested for reauthorization and/or additional funding? Yes, Reauthorization Only
If (Yes, Additional Funding), provide the following information: eMars Project Number (Agency, Fund): New Total Project Cost: $
Related to Previously Authorized Project: If the project is related to or a new phase of a project which was previously authorized please identify the project and action under which it was authorized.
Capital Project Type: New/Construction
Project Description
Additional/Description Justification The greatest benefit of this project will be improving student life and health. It will provide students with an easy and safe way to walk downtown. It will also bring more Frankfort residents on to campus--which will strengthen university-community relationships.
Project Measurements - Exum Center to rail-trail connection would be a 2,000 ft long, 8 ft.wide paved, including a 10 ft wooden bridge. Trail along University Drive to KSU Springhouse would be 2100 ft long. Residence halls to rail-trail connection would be 150 ft.long, 6 ft. wide, crushed limestone, including a 120 ft. wooden staircase.
Site - North of US60 Campus and South of US60 Campus. Prior Planning/and or Design - The project is dependent on municipal development of an abandoned rail bed into a rail-trail. In the various community meetings held to solicit public input, citizens have recommended any trail developed should include a link to the University.
Economic Development Impact - Rail-trails and their connectors have been found to have a positive economic impact on communities.
Project Budget
Project Budget was based on current estimating practices.
Existing Facility
Program Relocation
Phased Project
Universities Only: Type of Space Educational and General
Proposed Heat/Air conditioning Fuel Type Electric
Previous Request(s): Has this item been requested in a prior biennial budget request? Yes
If yes, identify the biennium/biennia; the project names(s); and the Cabinet/Agency. 2012-2014
PROJECT BUDGET
Has this project been reviewed by the Department for Facilities and Support Services? No
Fund Source Requested Requested FY 2013-14 FY 2014-15 Requested FY 2015-16 Requested Total
Restricted Funds01,025,0000
Total Funds01,025,0000
Cost Elements1,025,000
Site Survey/Preparation03,0000
Project Design077,0000
Movable Equipment/Furniture052,0000

62