2014-2016 Kentucky Branch Budget Capital Budget Request: Capital Project Record All dollar amounts rounded to next $1000
Capital Budget Record CBR-02
Branch:Executive Branch
Cabinet:Postsecondary Education
Agency:Postsecondary Education Institutions
Appropriation:Kentucky State University
Project Title:E2 Construct Business & Technology Center
KBUD Project Number:435U14C251
Project Budget
Private consultant and in-house estimate based on projected square footage requirements. Construction estimate is based on $380 per square foot.
Existing Facility
The proposed 65,200 square feet building will be a new structure to replace part of existing Bradford Hall which is currently housing the business school along with the Fine Arts Program. Bradford Hall has limited space, is unctionally obsolete, and has major structural problems resulting from failing foundation.
Program Relocation
The School of Business is presently housed in Bradford Hall. Bradford Hall is scheduled for major renovation and change of use.
Phased Project
Universities Only: Type of Space Educational and General
Proposed Heat/Air conditioning Fuel Type Coal
Previous Request(s): Has this item been requested in a prior biennial budget request? Yes
If yes, identify the biennium/biennia; the project names(s); and the Cabinet/Agency. 2012-2014 2010-2012 2008-2010 2006-2008 2004-2014 PROJECT BUDGFT Has this project been reviewed by the Department for Facilities and Support Services? No
Has this project been reviewed by the Department for Facilities and Support Services? No
Fund SourceRequested FY 2013-14Requested FY 2014-15Requested FY 2015-16Requested Total
Restricted Funds031,528,000031,528,000
Total Funds031,528,000031,528,000
Cost Elements
Site Survey/Preparation053,000053,000
Project Design02,037,00002,037,000
Movable Equipment/Furniture01,481,00001,481,000
Contingency Expense03,919,00003,919,000
Construction Costs024,038,000024,038,000
Total Costs031,528,000031,528,000
Completion Date: 05/2014
Method of Procurement (Acquisitions Only): Purchase
IMPACT ON OPERATING BUDGETFY1 AmountFY2 AmountFY3 AmountFY4 AmountFY5 Amount
Fund Source
General Fund217,300217,300217,300217,3000
Total Costs217,300217,300217,300217,3000
Cost Element
00000
Total Expenditures00000
Percent of Impact on Operating Budget for Programmatic Expenses?0
Operating Budget Priority
Operating Budget Priority
Cabinet: Agency: 4
45