2016-2018 Kentucky Branch Budget Capital Budget Request: Capital Construction Project Record All dollar amounts rounded to next $1000
Capital Budget Record CBR-02 Branch: Executive Branch Cabinet: Postsecondary Education Agency: Postsecondary Education Institutions Appropriation: Kentucky State University Project Title: School of Nursing
KBUD Project Number: 435U16C255
PriorityCapital Budget RequestSix-Year Capital Plan 2016-18
Cabinet:
Agency:21
PROJECT DOCUMENTATION
Location (County): Franklin
Reauthorization - Regular Capital Project: Is this a currently authorized project which is being requested for reauthorization and/or additional funding?
If (Yes, Additional Funding), provide the following information:
eMars Project Number (Agency, Fund):
New Total Project Cost: $ 13,014,000
Capital Project Type:
Project Description
The School of Nursing at Kentucky State University is poised to grow exponentially with the further development of present academic programs and the addition of new academic programs, such as the Doctor of Nursing Practice (BSN-DNP) program. Kentucky State University (KSU) is the first HBCU to offer a post-baccalaureate (BSN-DNP) Doctor of Nursing Practice program in the role of Adult Gerontology Primacy Care Nurse Practitioner.
KSU is blazing trails nationally as well. According to the American Association of Colleges of Nursing (AACN), the BSN-DNP program at KSU joins only 14% of nursing programs nationally that offer the BSN-DNP as an entry-level option into advanced practice (AACN, 2014). The inaugural BSN-DNP class will be admitted January 2015.
The available space in the existing facility is inadequate and not well designed for the needs that are required by the Nursing program. This project would provide adequate program space by means of the addition and the renovation of existing space to serve the administrative and academic needs of the program.
PROJECT BUDGET
Has this project been reviewed by the Department for Facilities and Support Services?
Fund SourceRequested FY 2015-16Requested FY 2016-17Requested FY 2017-18Requested Total
Bond Funds013,014,000013,014,000
Total Funds013,014,000013,014,000
Cost Elements
Land Acquisition0349,0000349,000
Site Survey/Preparation054,000054,000
Project Design0852,0000852,000
Movable Equipment/Furniture0355,0000355,000
Contingency Expense01,119,00001,119,000
Construction Costs010,285,000010,285,000
Total Costs013,014,000013,014,000
Completion Date: 08 / 2018
IMPACT ON OPERATING BUDGETFY1 AmountFY2 AmountFY3 AmountFY4 AmountFY5 Amount
Fund Source
General Fund62,0000000
Total Costs62,0000000
Cost Element
41