| 2024-25 Pool Projects | ORIGINAL Asset Preservation Pool Allocation | PROPOSED Asset Preservation Allocation | Increase/(Decrease) from this Pool for BOR Approval 8.7.26 | Total Project when combined with other Pool and Grant Funds | Status 7.15.26 | Updated Scope/Change Request |
|---|
| KSU - ASB Roof and Windows | $ 2,000,000 | $ 2,000,000 | $ - | $ 2,000,000 | In-Process Estimated Completion in August 2026 | None |
|---|
| KSU - Chandler Hall Renovation | $ 7,970,000 | $ 9,000,000 | $ 1,030,000 | $ 9,970,000 | Total Project $9,970,000\nIn-Process Estimated Completion in August 2026 | BOR Already Approved Scope Increase and Amount on 9.12.24 |
|---|
| KSU - The Halls Renovation Phase I | $ 1,000,000 | $ - | $ (1,000,000) | $ 750 | | Request to move funds to Student Center Renovation |
|---|
| KSU - Shauntee Hall Renovation | $ 2,680,000 | $ 2,680,000 | $ - | $ 15,680,000 | Funds rolled forward | None |
|---|
| KSU - Kentucky Hall Renovation - D 25 C 26 | $ 700,000 | $ 700,000 | $ - | $ 17,200,000 | Design In-Progress | None |
|---|
| KSU - Door Access Control Project | $ 1,500,000 | $ 1,500,000 | $ - | $ 1,500,000 | In-Process Estimated Completion in August 2026 | None |
|---|
| KSU - Building Evaluation & Asset Preservation (HVAC) | $ 3,650,000 | $ 3,260,400 | $ (389,600) | $ 3,260,400 | Spent $2,306,320 | None |
|---|
| KSU - Water Filtration Loop | $ - | $ 859,600 | $ 859,600 | $ 859,600 | Design and Acquisition | Requesting initiation of $859,600 project scope to install 3 loop filtration systems for the Central Boiler and Chiller system. |
|---|
| KSU - Site Improvements Phase 2 & 3 - Walks & Paving | $ 1,000,000 | $ 1,000,000 | $ - | $ 3,124,706 | In-Process Estimated Completion in December 2026 | Request to move $406,000 to Bradford (Windows), $1,000 to Exum (Permits), $14,000 to Hume (Skylight). |
|---|
| KSU - Hunter Hall Renovation | $ 7,500,000 | $ 7,500,000 | $ - | $ 8,250,000 | Bidding | Requesting CPE approval |
|---|