SARASOTA COUNTY

450301-1 - SARASOTA-BRADENTON AIRPORT LAND ACQUISITION PROJECT Type of Work: AVIATION ENVIRONMENTAL PROJECT

Phase Fund Code 2026 2027 2028 2029 2030

Capital DDR $2,323,368

DPTO $2,076,632

LF $4,400,000

Total for Project 450301-1 $8,800,000

PhaseFund Code20262027202820292030
CapitalDPTO$3,700,003
LF$3,700,000
Total for Project 450535-1$7,400,003

450535-1 - SARASOTA BRADENTON INTL AIRPORT GENERAL AVIATION FIS

Type of Work: AVIATION SAFETY PROJECT

450852-1 - SARASOTA BRADENTON INTL AIRPORT TERMINAL EXPANSION BAGGAGE IMPROVEMENT Type of Work: AVIATION CAPACITY PROJECT

PhaseFund Code20262027202820292030
CapitalDDR$2,300,000
LF$2,300,000
Total for Project 450852-1$4,600,000

Phase Fund Code 2026 2027 2028 2029 2030

Capital DDR $80,000

451402-1 - VENICE MUNICIPAL AIRPORT MAINTENANCE FACILITY Type of Work: AVIATION REVENUE/OPERATIONAL

DPTO $640,000

LF $20,000 $160,000

Total for Project 451402-1 $100,000 $800,000

PhaseFund Code20262027202820292030
CapitalDPTO$1,000,000$2,500,000$2,500,000
LF$1,000,000$2,500,000$2,500,000
Total for Project 453790-1$2,000,000$5,000,000$5,000,000

453790-1 - SARASOTA BRADENTON INTL AIRPORT TERMINAL PARKING GARAGE

Type of Work: AVIATION REVENUE/OPERATIONAL