WHEREAS, it is now the desire of the Township Council to act upon the Engineer's recommendation and to approve said Close-Out Change Order No. 1.
NOW, THEREFORE, BE IT RESOLVED by the Township Council of the Township of Jackson, County of Ocean and State of New Jersey, as follows:
DATED: 3-23-2021
RESOLUTION 147R-21
TITLE: AUTHORIZE AS-BUILT/CLOSE-OUT CHANGE ORDER NO. 3 AND FINAL TO THE CONTRACT BETWEEN THE TOWNSHIP OF JACKSON AND P&A CONSTRUCTION INC. FOR THE PROJECT KNOWN AS “2020 ROADWAY IMPROVEMENT PROGRAM” WHEREBY DECREASING THE CONTRACT AMOUNT BY $28,384.81 RESULTING IN AN ADJUSTED CONTRACT PRICE IN THE AMOUNT OF $809,868.65
WHEREAS, the Township of Jackson previously awarded a contract to P&A Construction Inc. for the project known as “2020 Roadway Improvement Program” in the amount of $838,253.46; and
WHEREAS, Township Engineer, Julio Vega, Jr., has recommended the approval of As-Built/Close-Out Change Order No. 3 and final, decreasing the contract by $28,384.81 as a result of final as-built quantities (per attached “Schedule A”); and
WHEREAS, the approval of this As-Built/Close-Out Change Order #3 and final will result in the return of the performance guarantee posted for this project. The return of said performance guarantee will be contingent upon the posting and acceptance of any required Maintenance Guarantee.
WHEREAS, it is now the desire of the Township Council to act upon the Engineer’s recommendation and to approve said Close-Out Change Order No. 3 and final.
NOW, THEREFORE, BE IT RESOLVED by the Township Council of the Township of Jackson, County of Ocean and State of New Jersey, as follows:
JANICE KISTY, R.M.C. TOWNSHIP CLERK