measures, containment, transportation, securing, or other engineering or institutional controls, whether to an unrestricted use or otherwise, designed to ensure that any contaminant is remediated in compliance with the applicable remediation standards. A remedial action continues as long as an engineering control or an institutional control is needed to protect the public health and safety and the environment, and until all unrestricted use remediation standards are met.
“Remediation” or “remediate” means all actions to investigate, clean up, or respond to any known, suspected, or threatened discharge of contaminants, including the preliminary assessment, site investigation, remedial investigation, and remedial action, or any portion thereof, provided, however, that “remediation” or “remediate” shall not include the payment of compensation for damage to, or loss of, natural resources.
No person shall deposit or place soil/fill material, or cause, allow, or permit soil/fill to be placed on any property in the Township of Jackson unless a permit is issued by the Township Engineer and any other applicable county, state or federal approval(s) or permit(s). No permit under this chapter shall be required for any development that requires a Land Use Approval from the Planning Board or Zoning Board of Adjustment provided the approval contains a condition(s) that meet the standards of this chapter and is so noted in any resolution of approval. As such, provided the land use applicant incorporates the requirements of this Ordinance as part of their application, and that approval is recommended by the respective board engineer, no additional permit would be required under this Ordinance.
Unless otherwise exempt, no permit shall be issued unless: (1) the applicant submits proof that the soil/fill material has been tested consistent with any applicable requirements set forth herein; (2) the soil/fill meets the definition of acceptable soil/fill; and (3) the application otherwise conforms with the standards of this chapter.
A person is not required to obtain a permit under this chapter for the following:
Minor filling associated with landscaping activities at any property where up to 15 cubic yards, or as otherwise allowed by the New Jersey Department of Environmental Protection under applicable regulations, per year of acceptable soil/fill material is being deposited.
Fill for septic installation and/or repair certified to be such by a licensed New Jersey engineer; or approved by the local health agency.
Virgin quarry products including, but not limited to, rock, stone, gravel, sand, clay and other mined natural products.
Acceptable soil/fill material being moved from one section of an owner's property to another section of the same property.
Soil/fill imported to or moved within a properly licensed Class B recycling facility.