Tampa Bay Florida Department of Transportation
US 92 (Dale Mabry Hwy) Traffic Signal Upgrades at El Prado Blvd and Interbay Blvd 436245-1-52-01
Project Details
Work TypeTraffic Signal Upgrades
PhaseCompleted
LimitsDale Mabry at El Prado Blvd and Interbay Blvd
Project StartMay 12, 2023
CityTampa
CountyHillsborough
RoadDale Mabry Highway SR 573 US 92
Construction Cost$3,397,760.34
Estimated CompletionLate 2023
ContractorAjax Paving Industries of Florida, LLC
Contact Information
Project Information
Maricelle Venegas 813-975-6204
RoadWork@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us
About
All construction activities associated with this project were completed on Monday, November 27, 2023.
This signalization upgrades project replaced the existing traffic signals with hurricane-resistant poles at US 92 (Dale Mabry Highway) and El Prado Boulevard, and Interbay Boulevard in South Tampa.
Construction activities were estimated to finish by end of 2023.