The stormwater runoff will be pretreated. All of the site runoff to the small-scale infiltration basins will be pretreated using bioretention basins or porous pavement. All the roof runoff to the small-scale infiltration basins will be pretreated with leaf screens.
South Hope Chapel Road is proposed to be widened along the project frontage. The proposed widening will add 6,402.44 sf of additional asphalt pavement and 1,861.45 sf of additional sidewalk on South Hope Chapel Road. An underground basin consisting of 60 linear feet of 24" perforated HDPE in South Hope Chapel Road is proposed to manage the increase in runoff. These basins are designed to fully infiltrate the increased runoff occurring during a 2-year storm, as per the County requirements.
The proposed development and stormwater management measures have been designed in compliance with the applicable Pinelands Commission regulations with regard to stormwater quantity, quality, and groundwater recharge requirements.
20 | Page