US 41 (Nebraska Avenue) Pedestrian Mid-Block Crosswalk at Idlewild Avenue 443492-2-52-01
| Project Details |
| Work Type | Pedestrian Safety Improvements |
|---|
| Phase | Completed |
|---|
| Limits | at Idlewild Avenue |
|---|
| Project Start | June 17, 2025 |
|---|
| City | Tampa |
|---|
| County | Hillsborough |
|---|
| Road | Nebraska Avenue (Hillsborough) US 41 |
|---|
| Construction Cost | $576,543 |
|---|
| Estimated Completion | Early 2026 |
|---|
| Contractor | Blacktip Services, Inc. |
|---|
All construction activities associated with this project were completed on December 11, 2025.
This safety improvement project installed a pedestrian hybrid beacon mid-block crosswalk at US 41 (Nebraska Avenue) to the north of Idlewild Avenue in Tampa.