| Project Details | |
| Work Type | Drainage repair |
|---|---|
| Phase | Completed |
| Limits | from north of the Anclote River bridge to south of Brittany Park Blvd |
| Project Start | August 2021 |
| Length | .2 miles |
| City | Tarpon Springs |
| County | Pinellas |
| Road | US 19 |
| Construction Cost | $1,422,150 |
| Estimated Completion | Early 2022 |
| Contractor | Gosalia Concrete Constructors, Inc |
This project is relocating sidewalk along the west side of US 19 between the Anclote River bridge and Brittany Boulevard in Pinellas County.
Other improvements include the regrading of a linear pond to improve the drainage in the area.
Construction is expected to finish in early 2022.
Contact Information
Project Information
David Alonso 727-575-8300
David.Alonso@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us