===== PAGE 1 ===== # SR 54 Repaving from Marathon Road to east of Gunn Highway 447954-1-52-01
Project Details
Work TypeResurfacing
PhaseCompleted
LimitsSR 54 from Marathon Rd to East of Gunn Hwy
Project StartJuly 14, 2025
Length1.95 Miles
CityOdessa
CountyPasco
RoadSR 54
Construction Cost$5.8 million
Estimated Completionearly 2026
ContractorAjax Paving Industries of Florida LLC
Contact Information
Project Information
John McShaffrey813-975-6930
john.mcshaffrey@dot.state.fl.us
Media Contact
Kayla Mejia813-975-6060
Kayla.Mejia@dot.state.fl.us
Image
Map data @2026 Google ## About The purpose of this project was to preserve and extend the life of the existing pavement, provide safety modifications, improve ADA facilities, and improve overall road operations. As of January 26, 2026, all construction activities associated with this project have been completed. The roadway was milled and resurfaced along with new pavement markings and signs. Traffic signals were upgraded at the SR 54 intersections of Trinity Boulevard, Community Drive, and Gunn Highway. A median opening east of Community Drive was closed.