Overhead Transmission Lines as % of Total Transmission System (Inside and Outside Service Territory)

Tier 2: 0% Tier 3: 0%

Customers have ever lost service due to an IOU PSPS event? ☐ Yes ☒ No

Have customers ever been notified of a potential loss of service to due to a forecasted IOU PSPS event? ☐ Yes ☒ No

Has developed protocols to pre-emptively shut off electricity in response to elevated wildfire risks? ☐ Yes ☒ No

Has previously pre-emptively shut off electricity in response to elevated wildfire risk? ☐ Yes ☒ No If yes, then provide the following data for calendar year 2020: N/A.

D. ORGANIZATION OF THE WILDFIRE MITIGATION PLAN

This Wildfire Mitigation Plan included the following elements:

  • Cross References to Statutory Requirements, Table 2
  • Objectives of the plan;
  • Roles and responsibilities for carrying out the plan;
  • Identification of key wildfire risks and risk drivers;
  • Description of wildfire prevention, mitigation, and response strategies and programs;
  • Metrics for evaluating the performance of the plan and identifying areas for improvement;
  • Review and validation of the plan; and
  • Timelines.

Table 2: Cross References to Statutory Requirements

RequirementStatutory LanguageLocation in WMP
Persons ResponsiblePUC § 8387(b)(2)(A): An accounting of the responsibilities of persons responsible for executing the plan.Section 3-B Page 8
Objectives of the PlanPUC § 8387(b)(2)(B): The objectives of the wildfire mitigation plan.Section 2 Page: 6