US 41 Erosion Protection from the Little Manatee River Bridge to Saffold Park Dr. 449485-1-52-01
| Project Details |
| Work Type | ErosionProtection and SeawallReplacement |
| Phase | Completed |
| Limits | from east of the Little Manatee River Bridge to Saffold Park Dr. |
| Project Start | July 16, 2022 |
| City | Ruskin |
| County | Hillsborough |
| Road | Tamiami Trail US 41 |
| Construction Cost | $403,261 |
| Estimated Completion | Fall 2022 |
| Contractor | Gosalia Concrete Constructors, Inc. |
| Contact Information |
| Project Information |
| Hamid Jafarian | 813-612-3200 |
| Hamid.Jafarian@dot.state.fl.us |
| Media Contact |
| Kayla Mejia | 813-975-6060 |
| Kayla.Mejia@dot.state.fl.us |
## About
All construction activities associated with this project were completed on Tuesday, August 30, 2022.
This project replaced the seawall and added erosion protection measures along the south side of US 41 from the east bank of the Little Manatee River to Saffold Park Drive in Hillsborough County.