FunctionDepartmentProgram
Wastewater System Renew & ReplaceWater & Sewer R&R Fund 535Wastewater Projects
AccountDESCRIPTIONActual FY 23-24Actual FY 24-25Adopted FY 25-26Projected FY 25-26Proposed FY 26-27
WASTEWATER PROJECTS
535-66-01Bay State South Sewer-----
535-66-08Rehab Belt Pre19,94229,913---
535-66-10Floating Solar Panels-----
535-66-16CR 44 Force Main77,892--205,259-
535-66-35Bates Avenue Sewer---35,000-
535-66-41Tank Cleaning11,398----
535-66-43Submersible Pump86,521-115,00097,500115,000
535-66-44Master Lift Station Upgrade--120,000120,000800,000
535-66-45Effluent Pump & Motor2,700--17,500100,000
535-66-46Coolidge Sewer Main Expansion1,613,489--460,600-
535-66-49Crane Truck----290,000
535-66-50Lift Station Control Panels----50,000
535-66-51Lift Station 7 Expansion--160,000160,000-
535-66-57Manhole Rehabilitation-----
535-66-59Pickup Truck54,831-55,00055,00055,000
535-66-62Sewer Cleaning Truck--170,000170,00080,000
535-66-65Umatilla Interconnection901,856----
535-66-70Eastern WWTP Expansion29,908----
535-66-74Loader Replacement----90,000
535-66-76Lift Station Generator79,928-175,000536,3151,160,000
535-66-77Lift Station #9 Rehabilitation456,851----
535-66-81McCullochs Alley Sewer258,290----
535-66-84Infiltration & Intrusion124,135-190,000253,500170,000
535-66-86Main WWTP Expansion8,636,778----
535-66-88Holding Pond Improvements1,592,925----
535-66-92Biological Process Equipment34,643-130,000229,279130,000
535-66-95Eastern Plant Turbine27,740--253,146-
535-66-96Old Eastern Plant Demolition----150,000
535-66-97Process & Clarif. Tank Rehab.----120,000
535-66-98Water Legislation Impact-----
535-66-99Heavy Equipment--165,000165,000625,000
TOTAL WASTEWATER PROJECTS14,009,82729,9131,280,0002,758,0983,935,000