3
| Block: 3902; Lot: 58 – Bellevue Estates, LLC |
| Location: 443 Leesville Road |
| P/F Major Subdivision to Subdivide into 4 Lots |
| Engineer: | PDS |
|---|
| Attorney: | Donna Jennings, Esq. |
|---|
| Date Complete: | 4/1/22 |
|---|
| Hearing Status: | Initial Testimony |
|---|
| Location: 443 Leesville Road |
| P/F Major Site Plan to Construct 4 Private Schools |
| Engineer: | PDS |
|---|
| Attorney: | Donna Jennings, Esq. |
|---|
| Date Complete: | 4/1/22 |
|---|
| Hearing Status: | Initial Testimony |
|---|
| Final Major Site Plan – Bike Path |
| Engineer: | Matrix New World Engineering |
|---|
| Attorney: | Ronald L. Shimanowitz, Esq. |
|---|
| Date Complete: | 10/18/21 |
|---|
| Decision Due Date: | Time Waived 6/30/22 |
|---|
| Hearing Status: | Testimony Given 12/6/21 |
|---|
| Eligible: Dolan, Campbell, Riker, Burnstein, Herman, Brito, Wall, Flemming, Riccardi, Haring, Hudak |
| Location: Denton Lane |
| P/F Major Subdivision to Create | 20 Residential Lots, 1 AH Lot 4 Units and 1 SW Lot |
|---|
| Engineer: | PDS |
|---|
| Attorney: | Adam Pfeffer, Esq. |
|---|
| Date Complete: | 9/1/21 |
|---|
| Decision Due Date: | Time Waived |
|---|
| Hearing Status: | Initial Testimony |
|---|
P/F Major Site Plan to Construct a 35,910 SF Warehouse Engineer: Dynamic Engineering
Attorney: Jennifer S. Krimko, Esq.
Date Complete: 10/12/21
Decision Due Date: Time Waived 6/30/22
Hearing Status: Testimony Given 12/6/21
Eligible: Dolan, Campbell, Riker, Burnstein, Herman, Brito, Wall, Flemming, Riccardi, Haring, Hudak
| Location: 463 Monmouth Road |
| P/F Major Site Plan and Minor Subdivision |
| Engineer: | PDS |
|---|
| Attorney: | Adam Pfeffer, Esq. |
|---|
| Date Complete: | 1/25/22 |
|---|
| Decision Due Date: | Time Waived |
|---|
| Hearing Status: | 3/7/22 |
|---|
| Eligible: Dolan, Campbell, Riker, Burnstein, Herman, Brito, Wall, Flemming, Riccardi, Haring, Hudak |