EXHIBIT C-18
TOWNSHIP OF JACKSON GENERAL CAPITAL FUND STATEMENT OF BONDS AND NOTES AUTHORIZED BUT NOT ISSUED AT DECEMBER 31, 2012
ORDINANCE NUMBERIMPROVEMENT DESCRIPTIONBALANCE DECEMBER 31, 20112012 AUTHORIZATIONSNOTES ISSUEDDEFERRED CHARGES FUNDEDBALANCE DECEMBER 31, 2012
19-09(i)Various Roadway Improvements$ 874,000$ 874,000
19-09(ii)Public Water Service Installation93,57593,575
19-00(iii)Acquisition of Office Equipment48,92548,925
19-09(iv)Implementation of Recycling Center33,25033,250
19-09(v)Acquisition of Equipment for Police Department83,60083,600
19-09(vi)Acquisition of Equipment for Public Works136,178136,178
19-09(vii)Acquisition of Passenger Bus for Senior Center61,75061,750
25-10Municipal Capital Improvements199,500199,500
25-10Township Recycling Center28,50028,500
25-10Technology Upgrades49,01049,010
25-10Police Department Equipment342,950342,950
25-10Department of Public Works Equipment1,501,8411,501,841
40-11Storm Water Basin1,332,313$ 1,332,313
03-12Road Improvements$ 1,330,0001,330,000
03-12DPW Equipment369,758369,758
03-12Ambulance142,500142,500
03-12Non-Passenger Vehicles190,000190,000
Total$ 4,785,392$ 2,032,258$ 5,485,337$ 1,332,313$ -
85