Summary of Anticipated Funding and Amount

Local Unit: Township of Jackson

PROJECT TITLE 2 ESTIMATED TOTAL COST BUDGET APPROPRIATION FUNDING AMOUNTS PER BUDGET YEAR

3a Current 2010 3b Future Years 4 Capital Improvement Fund 5a Capital Surplus 6 Grants-in-Aids and Other Funds BONDS AND NOTES

Street Lighting Capital Contribution 100,000.00 100,000.00 - 15,000.00 285,000.00

Municipal Buildings & Senior Center Improvements 100,000.00 100,000.00 - 32,500.00 617,500.00

7a General 7b Self Liquidating 7c Assessment 7d School

Road/Drainage Improvements-TBD-Approximate Co 800,000.00 800,000.00 - 155,000.00 200,000.00 2,945,000.00

Public Water Installation-Justice Complex 75,000.00 75,000.00 - 3,750.00 71,250.00

Legler Composting Site 25,000.00 25,000.00 - 4,750.00 - 90,250.00

Information Technology Upgrades 45,740.00 45,740.00 - 8,287.00 - 157,453.00

Police & Emergency Equipment 121,000.00 121,000.00 - 8,550.00 - 162,450.00

Toro 11" Mower with options 13,122.00 13,122.00 - 656.10 12,465.90

Transfer Station Repairs/Equipment 50,000.00 50,000.00 - 2,500.00 47,500.00

Automatic Brine Production Plant System 77,800.00 77,800.00 - 8,890.00 168,910.00

Wing Mower w/ Mower 95,000.00 95,000.00 - 4,750.00 90,250.00

Pickups 4X 4 (4) w/plows 120,000.00 120,000.00 - 6,000.00 114,000.00

DPW Large Vehicles/Equipment 1,120,000.00 1,120,000.00 - 121,000.00 2,299,000.00

Recreation Bleachers & Equipment 10,000.00 10,000.00 - 4,500.00 85,500.00

  • - - - -
  • TOTALS-ALL PROJECTS 2,902,662.00 2,902,662.00 - 383,633.10 - 200,000.00 7,289,028.90 - -
  • - - - -
  • - - - -

Section 2/20 Costs 150,000.00 150,000.00 - 7,500.00 142,500.00

SHEET 40d

C-5