| Project Details | |
| Work Type | Interchange Improvement |
|---|---|
| Phase | Completed |
| Limits | from south of Gandy Blvd to north of 78th Ave. |
| Project Start | Early 2023 |
| City | Pinellas Park |
| County | Pinellas |
| Road | Gandy Boulevard US 19 |
| Construction Cost | $2.3 Million |
| Estimated Completion | Fall 2023 |
| Contractor | Preferred Materials, Inc. |
As of September 7, 2023, all construction activities associated with this project have been completed.
This project will add additional left turn lane from southbound US 19 onto the eastbound Gandy Blvd entrance ramp. 78th Avenue will also be repaved between US 19 and 43rd Street.
Construction is underway and anticipated to be complete in the fall of 2023.
Contact Information
Project Information
Maddie Pfingsten 727-575-8334 roadwork@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060 Kayla.Mejia@dot.state.fl.us