===== PAGE 1 =====
# US 41 Repaving from Bullfrog Creek to Denver Street 434848-1-52-01
| Project Details |
| Work Type | Repaving |
| Phase | Completed |
| Limits | From Bullfrog Creek to Denver Street |
| Project Start | October 2018 |
| Length | 5 miles |
| City | Gibsonton Tampa |
| County | Hillsborough |
| Road | US 41 |
| Construction Cost | $15.6 million |
| Estimated Completion | Spring 2020 |
| Contractor | Pepper Contracting Services, Inc. |
Contact Information
Project Information
Kouser Manzer
813-612-3200
Kouser.Manzer@dot.state.fl.us
Media Contact
Kayla Mejia
813-975-6060
Kayla.Mejia@dot.state.fl.us
Google
Adamsville
Map data ©2020 Google
## About
## FINAL ACCEPTED ON MARCH 24, 2020
This project includes repaving US 41 from north of Bullfrog Creek to Denver Street in Hillsborough County.
Other construction activities include making improvements to turn lanes, traffic signals, and roadway lighting.
In addition, crews are replacing the asphalt intersections at Pendola Point Road and Port Sutton Road with concrete to better handle the heavy truck traffic on this corridor.
Construction activities are occurring during daytime and nighttime hours.
Motorists are advised to use caution while traveling through the work zone and allow for extra travel time as major delays are likely.
Completion is anticipated spring of 2020.
This project has been combined with the installation of new sidewalks to both sides of US 41 (50th street) between Denver Street and South 30th Avenue (Project Number 439038-1-52-01).