US 98/SR 50 Repaving from south of Jasmine Drive to Mondon Hill Road 447948-1-52-01
Project Details
| Project Details |
| Work Type | Resurfacing |
|---|
| Phase | Completed |
|---|
| Limits | US 98/SR 50 from south of Jasmine Dr. to Mondon Hill Rd. |
|---|
| Project Start | May 19, 2025 |
|---|
| Length | 3.7 Miles |
|---|
| City | Brooksville |
|---|
| County | Hernando |
|---|
| Road | SR 50 US 98 |
|---|
| Construction Cost | $6 million |
|---|
| Estimated Completion | October 22, 2025 |
|---|
| Contractor | C.W. Roberts Contracting, Inc. |
|---|
As of October 22, 2025, all construction activities associated with this project have been completed.
This project resurfaced the asphalt roadway of US 98 / SR 50 from south of Jasmine Drive to Mondon Hill Road in Hernando County. Highway signing and pavement markings were also part of the project improvements.