| Project Details | |
| Work Type | Repaving |
|---|---|
| Phase | Completed |
| Limits | McKay Avenue to Cleveland Street |
| Project Start | September 2019 |
| City | Tampa |
| County | Hillsborough |
| Road | Dale Mabry Highway US 92 |
| Construction Cost | $2.4 million |
| Estimated Completion | Early 2020 |
| Contractor | Hubbard Construction Company |
Contact Information
Project Information
Jessica Lyons 813-612-3200
Jessica.Lyons@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us
The Florida Department of Transportation's contractor, Hubbard Construction Company, is repaving Dale Mabry Highway (US 92) between McKay Avenue and Cleveland Street in South Tampa.
Other improvements include installing new hurricane resistant traffic signals at Swann Avenue and Azeele Street.
Construction activities are occurring during daytime and nighttime hours.
Motorists can expect nightly lane closures from 9:30 pm to 6:30 am.
The $2.4 million project is scheduled to finish in early 2020.