Tampa Bay Florida Department of Transportation
Alt US 19 (N. Pinellas Ave) Sidewalk from Oscar Hill Rd to Dixie Hwy 441441-2-52-01
Project Details
Work TypeSidewalk
PhaseCompleted
Limitsfrom Oscar Hill Rd to Dixie Hwy
Project StartAugust 2020
Length.3 miles
CityTarpon Springs
CountyPinellas
RoadAlt US 19 Pinellas Avenue
Construction Cost$1,622,282
Estimated CompletionSpring 2021
ContractorDavid Nelson Construction Co.
Contact Information
Project Information
Sarah Gansz 727-575-8300
Sarah.Gansz@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us
About
FINAL ACCEPTED ON MARCH 4, 2021
This project will add sidewalks along both sides of Alt. US 19 (Pinellas Avenue) between Oscar Hill Road and Dixie Highway in Tarpon Springs.
In addition, a new mid-block pedestrian crossing with a rectangular rapid flashing beacon will be installed between Anclote Road and Fulton Street.
The $1.6 project is expected to finish in the spring of 2021.