# US 301 Intersection High Friction Surface Treatment at Stacy Road 254677-5-23
| Project Details |
| Work Type | Safety Improvements |
| Phase | Completed |
| Project Start | Late 2021 |
| City | Thonotosassa |
| County | Hillsborough |
| Road | US 301 US 41 |
| Construction Cost | $569,132.37 |
| Estimated Completion | Summer 2022 |
| Contractor | Cone & Graham, Inc. |
| Contact Information |
| Project Information |
| Randy Aebrsold | 727-575-8300 |
| Randall.Aebersold@dot.state.fl.us |
| Media Contact |
| Kayla Mejia | 813-975-6060 |
| Kayla.Mejia@dot.state.fl.us |
## About
As of January 18, 2022, all work associated with this project has been completed.
This design-build project is making roadway improvements at the intersection of US 301/SR 41 and Stacy Road in Hillsborough County.
Elements of work shall include but are not limited to roadway milling and resurfacing with a high surface friction treatment. These improvements will protect against skidding and provide a safe travel path for vehicles.
Status: Construction is anticipated to finish in the summer of 2022