===== PAGE 1 ===== ## Safety Improvements - Various Locations in Pasco County 254677-6-18 ## Project Details
Work TypeSafety Improvements
PhaseCompleted
CityHoliday Tarpon Springs
CountyPasco
RoadAlt US 19 US 19
Construction Cost$237,000
ContractorCone & Graham, Inc.
Contact Information
Project Information
Bryce Johns727-575-8334
Bryce.Johns@dot.state.fl.us
Media Contact
Kayla Mejia813-975-6060
Kayla.Mejia@dot.state.fl.us
## Key Vista Nature Park
Image
Map data ©2026 INEGI ## About All construction activities associated with this project are complete as of December 22, 2025. The Florida Department of Transportation's Design-Build Firm, Cone & Graham, Inc., made safety improvements at various locations in Pasco County: ## SR 595 / ALT US 19 Location 1: SR 595 / ALT US 19 from Anclote Boulevard to north of Louis Avenue ## SR 55 (US 19) Location 2: SR 55 (US 19) at Panorama Avenue Location 3: SR 55 (US 19) at Lange Road Location 4: SR 55 (US 19) at Tahitian Circle Location 5: SR 55 (US 19) at Camry Drive Elements of work included the installation of raised separators as well as repaving and shoulder widening. Construction activities are complete as of December 22, 2025. ***** ***** What is design-build? Design-build is a method of project delivery in which one entity - the design-build team - works under a single contract with the FDOT (or any owner) to fully design and construct a project. The contract work covers from initial design through construction completion. This contract type typically allows for faster construction of a project as design and construction can be on-going simultaneously.