Tampa Bay Florida Department of Transportation
I-275 SB ramp to I-75 NB (Manatee County) Bridge Deck Replacement 436299-1-52-01
Project Details
Work TypeBridge Deck Replacement
PhaseCompleted
LimitsManatee County I-275 southbound ramp to northbound I-75
Project StartJuly 29, 2018
RoadI-275 I-75
Construction Cost$8 million
Estimated Completion2020
ContractorCone & Graham, Inc.
Contact Information
Media Contact Lauren Hatchell 941-708-4418 Lauren.hatchell@dot.state.fl.us
About
This project was completed in May 2020.
This project involves replacing the concrete bridge deck of the southbound I-275 ramp to northbound I-75 in Manatee County.
This work requires the complete closure of the ramp. All traffic choosing to travel from SB I-275 in Manatee County to NB I-75 will be detoured off the interstate at US 41.
For additional details; http://www.swflroads.com/i275/i75bridgedeckreplacement.pdf