===== PAGE 1 ===== SR 60 (Brandon Boulevard) Intersection Upgrades from Brandon Town Center Drive to Gornto Lake Road 436041-1-52-01
Project Details
Work TypeIntersection upgrades
PhaseCompleted
LimitsFrom Brandon Town Center Drive to Gornto Lake Road
Project StartJanuary 3, 2022
CityBrandon
CountyHillsborough
RoadBrandon Boulevard SR 60
Construction Cost$3.7 million
Estimated CompletionFall 2023
ContractorPCS Civil, Inc.
Contact Information
Project Information
Maricelle Venegas813-975-6204 roadwork@dot.state.fl.us
Media Contact
Kayla Mejia813-975-6060 Kayla.Mejia@dot.state.fl.us
Image
## About All construction activities associated with this project were completed on Friday, November 17, 2023. This project added turn lanes to SR 60 (Brandon Boulevard) between Brandon Town Center Drive and Gornto Lake Road in Hillsborough County. Other improvements included: - modifying the existing directional opening by eliminating the eastbound SR 60 (Brandon Boulevard) left turn onto Lake Kathy Drive (motorist to continue eastbound and make a U-turn at the signalized Gornto Lake Road intersection). - replacing the traffic signals at Brandon Town Center Drive.