SR 60 (Brandon Boulevard) Intersection Upgrades from Brandon Town Center Drive to Gornto Lake Road 436041-1-52-01

Project Details
Work TypeIntersection upgrades
PhaseCompleted
LimitsFrom Brandon Town Center Drive to Gornto Lake Road
Project StartJanuary 3, 2022
CityBrandon
CountyHillsborough
RoadBrandon Boulevard SR 60
Construction Cost$3.7 million
Estimated CompletionFall 2023
ContractorPCS Civil, Inc.

About

All construction activities associated with this project were completed on Friday, November 17, 2023.

Contact Information

Project Information

Maricelle Venegas 813-975-6204 roadwork@dot.state.fl.us

This project added turn lanes to SR 60 (Brandon Boulevard) between Brandon Town Center Drive and Gornto Lake Road in Hillsborough County.

Other improvements included:

  • modifying the existing directional opening by eliminating the eastbound SR 60 (Brandon Boulevard) left turn onto Lake Kathy Drive (motorist to continue eastbound and make a U-turn at the signalized Gornto Lake Road intersection).
  • replacing the traffic signals at Brandon Town Center Drive.