| Project Details | |
| Work Type | Repaving |
|---|---|
| Phase | Completed |
| Limits | From Manatee County Line to north of CR 672 (Big Bend Road) |
| Project Start | January 2020 |
| City | Apollo Beach Ruskin Sun City Center |
| County | Hillsborough |
| Road | I-75 |
| Construction Cost | $20.1 million |
| Estimated Completion | Early 2021 |
| Contractor | Preferred Materials. Inc. |
This project is repaving approximately 16 miles along I-75 between the Manatee County Line and CR 672 (Big Bend Road) in Hillsborough County.
Construction on the $20 million project is expected to finish in early 2021.