I-4 Wildlife Crossing Virtual Public Workshop FPID Number: 201214-8-52-01
Florida Department of TRANSPORTATION
Project Schedule and Costs
Project Phases
Status
Cost Estimate
Right-of-way acquisition
Fall 2021
$ 1.3 Million
Design
December 2023
$ 1.2 Million
Construction
Not funded
$ 8.2 Million
Construction Inspection
Not funded
$ 1.2 Million
Total Cost
$ 11.9 Million