122

ORDINANCE NUMBERIMPROVEMENT DESCRIPTIONBALANCE DECEMBER 31, 20162017 AUTHORIZATIONSCANCELLEDBALANCE DECEMBER 31, 2017
21-15Section 20 Costs$ 0.70$ -$ 0.70$ -
23-15JetVac and Sweeper1,075,000.00-1,075,000.00-
17-16DPW Equipment/Gas Boy - Cap Project545,300.00--545,300.00
17-16Misc. Public Works Projects/Repairs66,500.00--66,500.00
17-16Justice Complex109,250.00--109,250.00
17-16Police CAD/Vehicles313,500.00--313,500.00
17-16Roads/Sidewalks/Drainage950,000.00--950,000.00
17-16Section 20 Costs297,682.50--297,682.50
09-17Road/Sidewalks/Drainage-949,984.12-949,984.12
09-17DPW Projects & Repairs-584,735.92-584,735.92
09-17Assessor Vehicle-23,750.00-23,750.00
09-17Police Equipment & Vehicle-259,355.18-259,355.18
09-17Section 20 Costs-272,673.78-272,673.78
Total$ 3,357,233.20$ 2,090,499.00$ 1,075,000.70$ 4,372,731.50

TOWNSHIP OF JACKSON GENERAL CAPITAL FUND SCHEDULE OF BONDS AND NOTES AUTHORIZED BUT NOT ISSUED AT DECEMBER 31, 2017