===== PAGE 1 ===== SR 39 (Paul Buchman Highway) Repaving from Hillsborough County Line to south of Bay Avenue 439830-1-52-01
Project Details
Work TypeRepaving
PhaseCompleted
LimitsFrom Hillsborough County Line to south of Bay Avenue
Project StartJune 13, 2020
Length.7 miles
CityZephyrhills
CountyPasco
RoadPaul Buchman Highway SR 39
Construction Cost$682,863.27
Estimated CompletionOctober 2020
ContractorC.W. Roberts Contracting, Inc.
Contact Information
Project Information
Salem Dhouib813-612-3200
Salem.Dhouib@dot.state.fl.us
Media Contact
John McShaffrey813-975-6930
john.mcshaffrey@dot.state.fl.us
Image
Map data ©2020 ## About ## Construction has been completed and the project final accepted on October 16, 2020 This project repaved SR 39 (Paul Buchman Highway) between the Hillsborough County line and Bay Avenue in Crystal Springs. The pavement was also widened to allow the bicycle lanes to be extended through the County Line Road / Florida Avenue intersection.