### SR 54 Repaving from east of Gunn Highway to east of Crossings Blvd. and Black Lake Road 447953-1-52-01
| Project Details |
| Work Type | Resurfacing |
| Phase | Completed |
| Limits | SR 54 from east of Gunn Hwy to east of Crossings Blvd and Black Lake Rd |
| Project Start | June 23, 2025 |
| Length | 3.87 Miles |
| City | Odessa |
| County | Pasco |
| Road | SR 54 |
| Construction Cost | $6.3 million |
| Estimated Completion | early 2026 |
| Contractor | Hubbard Construction Company |
| Contact Information |
| Project Information |
| John McShaffrey\n813-975-6930 | john.mcshaffrey@dot.state.fl.us |
| Media Contact |
| Kayla Mejia\n813-975-6060 | Kayla.Mejia@dot.state.fl.us |
| |
LAKE POLO Map data ©2026 Google
## About
As of January 29, 2026, all construction activities associated with this project have been completed.
This project milled and repaved SR 54 from east of Gunn Highway to east of Crossings Boulevard (Odessa area of Pasco County) to preserve and extend the life of the pavement. It also included safety modifications and ADA facility improvements along SR 54.
Minor drainage and signing/pavement marking work took place. All improvements were made within the existing rights-of-way.
Black Lake Road was also repaved as part of this project.
Construction began June 23, 2025.