SR 574 (Martin Luther King Jr. Boulevard) Corridor Lighting Retrofit from I-4 to Laura Street 254677-5-42

Project Details
Work TypeSafety Improvements
PhaseCompleted
Limitsfrom I-4 to Laura Street
Project StartMay 30, 2023
CityMango Seffner Tampa
CountyHillsborough
RoadDr Martin Luther King Jr Boulevard I-4 SR 574
Construction Cost$300,000
Estimated CompletionSummer 2023
ContractorCone & Graham, Inc.

About

As of August 9, 2023, all construction activities associated with this project have been completed.

The Florida Department of Transportation's Design-Build firm, Cone & Graham, Inc., is making improvements to roadway lighting along SR 574 (Martin Luther King Jr. Boulevard) from I-4 to Laura Street in Hillsborough County.

Safety improvements include installing new light poles and retrofitting existing light poles along this roadway. This project is estimated to finish by late 2023.

Contact Information

Project Information

Maddie Pfingsten

727-575-8334

RoadWork@dot.state.fl.us

Media Contact

Kayla Mejia 813-975-6060

Kayla.Mejia@dot.state.fl.us