As noted above, the proposed peak flows meet the above reductions, thereby achieving off-site stability, therefore; this section is not applicable.
As noted above, the proposed peak flows meet the above reductions, thereby achieving off-site stability, therefore; this section is not applicable.
In addition to ensuring erosion does not occur at the point of discharge, areas downstream and beyond the immediate area of site development may be damaged due to erosive forces resulting from extended duration of hydrograph peak flows. An unintended consequence of the practice of detaining and slowly releasing stormwater is the ability for peak flows to be sustained for longer periods of time, offering an opportunity for upstream discharges to coincide with project site discharges. The resulting combined discharge may be equal to or even exceed that of the pre-development condition.
To limit the potential for such an occurrence the designer may choose either of two approaches for downstream stability protection:
2-year storm – 50% of the predevelopment peak
10-year storm – 75% of the predevelopment peak