| Project Details |
| Work Type | Repaving |
|---|
| Phase | Completed |
|---|
| Limits | from Charlie
Griffin Road to
Alexander Street |
|---|
| Project Start | May 30, 2023 |
|---|
| Length | .6 miles |
|---|
| City | Plant City |
|---|
| County | Hillsborough |
|---|
| Road | James L Redman
Parkway
SR 39 |
|---|
| Construction
Cost | $3.3 million |
|---|
| Estimated
Completion | Early 2024 |
|---|
| Contractor | CW Roberts
Contracting, Inc. |
|---|
All construction activities associated with this project were completed on Thursday, March 14, 2024.
This project repaved SR 39 (James L. Redman Parkway) between Charlie Griffin Road and Alexander Street in Plant City.
Additional improvements:
Contact Information
Project Information
Maricelle Venegas 813-975-6204
RoadWork@dot.state.fl.us
added a right turn lane from southbound James L. Redman Parkway onto westbound Alexander Street
widened the existing right turn lane from Alexander Street onto southbound James L. Redman Parkway
The $3.3 million project began May 30, 2023, and finished March 14, 2024.