US 301 Repaving from Breckenridge Pkwy/Sligh Ave to I-75 440252-1-52-01

Project Details
Work TypeRepaving
PhaseCompleted
Limitsfrom Breckenridge Pkwy/Sligh Ave to I-75
Project StartSeptember 2020
CityTemple Terrace
CountyHillsborough
RoadUS 301
Construction Cost$3.2 million
Estimated CompletionSummer 2021
ContractorHubbard Construction Company

About

FINAL ACCEPTED AND COMPLETED ON MAY 7, 2021

The project repaved US 301 between Breckenridge Parkway and I-75 in Hillsborough County.

Construction began September of 2020 and finished on May 7, 2021.