forebay is provided for the surface SSIB's to provide water quality and TSS removal in accordance with adopted regulations. The overall system will maintain peak discharge rates to less than those required by State adopted Stormwater Management criteria. The following is a summary of the runoff from the site:
A. Pre-developed Conditions
Storm EventExist Peak Discharge from Site (CFS)Allowable Peak Discharge (CFS)
2 year1.430.71
10 year2.321.74
100 year5.234.18
C. Post-developed Conditions
Post-developed run-off rates are tabulated as follows:
Storm EventAllowable Permissible Peak Discharge (CFS)Post-Developed Discharge (CFS)Status
2 year0.710.24Complies
10 year1.740.95Complies
100 year4.183.71Complies