Project Details
| Phase | Construction |
|---|---|
| Limits | from east of the bridge to Ben T. Davis Beach |
| Project Start | October 28, 2026 |
| Length | 5.5 miles |
| City | Tampa |
| County | Hillsborough |
| Road | SR 60 |
| Construction Cost | $1.6 million |
| Estimated Completion | Early 2027 |
| Contractor | Turtle Infrastructure Partners, LLC |
Contact Information
Project Information
Maricelle Venegas 813-975-6204
Maricelle.Venegas@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us
This improvement project is making repairs to the multi-use trail along the south side of SR 60 (Courtney Campbell Causeway) in Hillsborough County. Most construction activities are taking place during daytime hours. At times, section of the multi-use trail will temporarily close to motorists, pedestrian and cyclists while crews make asphalt and wall repairs throughout the duration of the project. Motorists traveling along SR 60 (Courtney Campbell Causeway) will not be impacted by this multi-use trail improvement project. Construction activities are expected to finish during early 2027
Construction activities are expected to finish during early 2027.
For more information on this project, or to sign-up to receive construction updates and traffic alerts, please visit FDOTtampabay.com (Project Number: 456290-1-52-01) Last Updated: 10/29/2026